Union City

Named in 9 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
9projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
UNION CITY - YATES 230kV (WHITE) LINE REBUILD
Rebuild 23.4 miles of the Union City - Yates 230kV (White) line with bundled 200C 1351 ACSS Martin conductor.
TEAMS 17900 · plan p.107 · zone 208
GPC In the plan
p.9
Jun 1, 2026 No change Union City, Yates
CC - SHUGART (NETWORK IMPROVEMENTS)
GPC will rebuild and reconfigure the Line Creek 230kV substation and connect the Morrow - Yates 230kV line and the Union City - Yates 230kV White and Black lines into Line Creek. Build two short lines from Line Creek to Shugart Farms (0.3 miles each) with 100C 1351 ACSR Martin conductor.
TEAMS 18736 · plan p.123 · zone 208
GPC In the plan
p.10
Jun 1, 2027 No change Morrow, Union City, Yates
CC - FAYETTEVILLE AREA TRANSMISSION NEEDS
Build a new 500/230kV substation (Ashley Park) splitting the Ohara - Union City 500kV line. Install two 500/230kV auto transformers at the Ashley Park station. Build two new 230kV lines (6 miles each) from Ashley Park to the high side of the customer substations. The new lines will be built with bundled 200C 1351 ACSS Martin conductor.
TEAMS 20018 · plan p.84 · zone 208
GPC In the plan
p.7
Apr 1, 2026 No change Ashley Park, Ohara, Union City
CC - STONEWALL TELL ROAD
Build a 4 miles 230kV line segment, using 200C 1351 ACSS Martin conductor, to loop in the Stonewall Tell Road station into the East Point - Union City 230kV (White) line.
TEAMS 20216 · plan p.91 · zone 208
GPC In the plan
p.7
Jun 1, 2026 No change East Point, Stonewall Tell Road, Union City
UNION CITY - YATES 230kV (BLACK) LINE REBUILD
Rebuild the Union City - Yates 230kV (Black) line with bundled 200C 795 ACSS Martin conductor. Replace limiting elements at Union City, Fairburn #1 and Line Creek substations.
TEAMS 20274 · plan p.185 · zone 208
GPC In the plan
p.14
Jun 1, 2028 No change Union City, Yates
EAST POINT - UNION CITY (WHITE) 230kV REBUILD
Rebuild 4.5 miles of 230kV line on the East Point - Union City 230kV (White) line with 200C 1351.5 ACSS Martin
TEAMS 20690 · plan p.304 · zone 208
GPC In the plan
p.22
May 1, 2035 Delayed from 2031 to 2035 East Point, Union City
UNION CITY - YATES 230kV (WHITE) SWITCH AND TRAP REPLACEMENT
Replace the limiting elements at Union City and Yates substations along the Union City - Yates 230kV (White) line.
TEAMS 20691 · plan p.108 · zone 208
GPC In the plan
p.9
Jun 1, 2026 No change Union City, Yates
CC - VILLA RICA UPGRADES (NETWORK IMPROVEMENTS)
Add a new 500/230kV auto transformer at Villa Rica, and loop in and out the Bowen - Union City 500kV line into Villa Rica. Reconfigure the 230kV yard.
TEAMS 20774 · plan p.158 · zone 211
GPC In the plan
p.12
Jun 1, 2028 No change Bowen, Union City
GTC: CAVENDER DRIVE 500/230kV AUTO TRANSFORMER
Cavender Drive will become a 500/230kV station looping in the Villa Rica - Union City 500kV line and installing a 500/230kV auto transformer.
TEAMS 21013 · plan p.246 · zone 201
GTC In the plan
p.18
Jun 1, 2030 No change Union City, Villa Rica

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.