South Griffin
Named in 5 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTC, MEAGproject sponsor
5projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: BARNESVILLE - BIG SOUTH GRIFFIN 230kV PROJECT Construct a new 19 miles, 230kV line from South Griffin substation - Barnesville Primary substation with 200C 1351 ACSS conductor. TEAMS 08458 · plan p.200 · zone 213 |
GTC | In the plan p.15 |
Jun 1, 2029 | Delayed from 2028 to 2029 | BARNESVILLE, Barnesville Primary, Big South Griffin, South Griffin |
| GTC: MCDONOUGH - SOUTH GRIFFIN 115kV REBUILD In 2028, rebuild 5.8 miles from McDonough to Locust Grove to Luella Jct using 200C 1351 ACSS Martin. Replace all limiting elements including switches and jumpers. TEAMS 21282 · plan p.165 · zone 208 |
GTC | In the plan p.13 |
Jun 1, 2028 | New project | MCDONOUGH, South Griffin |
| HAMPTON AREA 115 TO 230kV LINE CONVERSIONS Convert Hampton – Ohara 115kV and Jonesboro – Ohara 115kV to create a new Jonesboro – Hampton 230kV line. Convert Hampton – South Griffin 115kV to 230kV operation. Loop in Jonesboro - Ohara 115kV through Bonanza so it is not radial. Install a new 230/115kV auto transformer at Jonesboro. TEAMS 21566 · plan p.169 · zone 208 |
GPC | In the plan p.13 |
Jun 1, 2028 | New project | Hampton, Jonesboro, Ohara, South Griffin |
| MEAG: BIG SOUTH GRIFFIN 230/115kV SUBSTATION Build a new 230/115kV substation and relocate all lines except for the South Coweta and Griffin #1 115kV lines from the existing South Griffin substation. Terminate the newly converted Hampton - South Griffin 230kV line. Install two 230/115kV auto transformers. TEAMS 21568 · plan p.175 · zone 208 |
MEAG | In the plan p.13 |
Jun 1, 2028 | New project | Big South Griffin, Hampton, South Griffin |
| GTC: OHARA - SOUTH GRIFFIN 230kV LINE RECONDUCTOR Reconductor 23 miles of the Ohara - South Griffin 230kV line section using 200C 1351 ACSS Martin. TEAMS 21594 · plan p.209 · zone 208 |
GTC | In the plan p.16 |
Jun 1, 2029 | New project | Ohara, South Griffin |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner