Towaliga River
Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).
Described as new. The quoted wording calls this substation new. “new Towaliga River 230kV substation” — TEAMS 20717, plan p.149
The plan prints no county for this substation, and no utility project page found names one for it.
Location
33.2735, -84.0650 · Butts County, GA · view on a map
Point published by the utility. The utility publishes this point, on a project map or in a filing. Accurate to about ±300 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Printed by the sponsor: Georgia Power's Tomochichi – Towaliga River project page embeds its project map's configuration, with a location titled "Towaliga River Substation" at lat 33.27350709, lng -84.06503473; the printed path of proposed line 2 ends at exactly that position and line 1 ends ~60 m from it. Web-map marker, not a survey point: the page says "MAP NOT BASED ON FIELD SURVEY DATA" and "Structure and Line Locations based on Pre-Engineering data and subject to change". Accuracy ±300 m is a station-footprint allowance around a marker, not a survey figure.
County: the Census county at this point.
Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.149 · Georgia Power, Tomochichi – Towaliga River Project page (n/a (retrieved 2026-11-20)), About the Project; Project Map. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| CC - TOMOCHICHI 500/230kV SOLUTION (NETWORK IMPROVEMENTS) Build the new Tomochichi 500/230kV station splitting the Ohara - Scherer 500kV line. Build two 230kV lines from the new Tomochichi substation to the new Towaliga River 230kV substation with bundled 200C 1351 ACSS Martin. One will be 6 miles, and one will be 5 miles. Also adjust the tap settings on the 500/230kV transformer to address high voltage concerns on the 230kV system. TEAMS 20717 · plan p.149 · zone 208 |
GPC | In the plan p.12 |
Sep 15, 2027 | Delayed within 2027 | Ohara, Scherer, Tomochichi, Towaliga River |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.