Bedington
Named in 9 PJM planning documents for 13 projects, from October 8, 2024 to October 16, 2026.
Also printed as: Bedington Substation
PJM interconnection queue
A PJM queue substation page has the same name: Bedington (WV) — 2 queue requests filed, 2 active.
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Bedington – Eagle 138 kV b3976.1 |
Not printed | $1.96M | 06/01/2030 | Not printed | 2025-11-14 SRRTEP Western |
| Bedington – Eagle 138 kV | Not printed | $1.96M | 06/01/2030 | Not printed | 2025-10-17 SRRTEP Western |
| Marlowe Substation APS-2023-027 · s3131.1 |
Not printed | $ 0.3 M | 10/27/2023 | Not printed | 2024-10-08 TEAC |
| Bedington Substation APS-2023-028 · s3162.1 |
Not printed | $21.8M | 06/01/2027 | Not printed | 2024-10-08 TEAC |
| Bedington – Marlowe BMA 138 kV Line New Customer APS-2023-030 · s3103.1 |
Not printed | $30.4M | 6/30/2026 | Not printed | 2024-10-08 TEAC |
| Bedington – Doubs 500 kV Misoperation Relays APS-2023-057 · s3163.1 |
Not printed | $ 6.95 M | 02/28/2025 | Not printed | 2024-10-08 TEAC |
| Misoperation Relay Projects APS-2024-008, APS-2024-011, APS-2024-013, APS-2024-015, APS-2024-016, APS-2024-024, APS-2024-030 to APS-2024-034 · s3470.1, s3471.1, s3472.1, s3473.1, s3474.1, s3475.1, s3476.1, s3477.1, s3478.1, s3479.1, s3480.1 |
Not printed | Not printed | Not printed | Not printed | 2024-10-08 TEAC |
| Misoperation Relay Projects APS-2024-016, APS-2024-024, APS-2024-030, APS-2024-031 · s3474.1, s3475.1, s3476.1, s3477.1 |
Not printed | Not printed | Not printed | Not printed | 2026-09-08* SRRTEP Western |
| Bedington No. 3 500/138 kV Transformer APS-2024-027 · s3452.1 |
Not printed | $18.7M | 12/31/2027 | Not printed | 2024-10-08 TEAC |
| Misoperation Relay Projects APS-2024-039, APS-2024-041 to APS-2024-045, APS-2024-048 to APS-2024-051 |
Not printed | Not printed | Not printed | Not printed | 2024-10-08 TEAC |
| Bedington – Marlowe 138 kV Line APS-2025-007 · s3667.1 |
Not printed | $4.00M | 7/26/2029 | Not printed | 2025-10-08 TEAC |
| Misoperation Relays APS-2026-051 |
Not printed | Not printed | Not printed | Not printed | 2026-10-16 SRRTEP Western |
| New Customer Connection APS-2026-078 |
Not printed | Not printed | 1/1/2028 | approximately 200 MW | 2026-10-16 SRRTEP Western |
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | 6/30/2026 → 2/28/2025 | 2024-10-08 | Not reported |
| Substations named | ANTIETAM; BEDINGTON; BELMONT; BETHELBORO; CARNEGIE; CHARLEROI; DONEGAL; E HAGERSTOWN; EAST HAGERSTOWN; EDGELAWN; HAMPSHIRE; IRON BRIDGE; MARLOWE; PAPER CITY; RENO TAP; RIDGELEY; RIDGWAY; TIDD; TRISSLER; WEIRTON; YUKON → ANTIETAM; BETHELBORO; CHARLEROI; EAST HAGERSTOWN; PAPER CITY; RIDGWAY; YUKON | 2024-10-08 | Not reported |
| Substations named | ANTIETAM; BACK FORK; BEDINGTON; CANAAN VALLEY; COWEN; CRUPPERNECK; DOUBLE TOLL GATE; EAST HAGERSTOWN; GLENVILLE; GREENWOOD; NIPETOWN; PARAMOUNT; REDBUD; REID; RINGGOLD; SENECA CAVERNS; SHAFFERS CORNER; SHAFFERS CORNERS; SPRINGDALE; WESTON; WILLIAM → ANTIETAM; BACK FORK; BEDINGTON; CANAAN VALLEY; COWEN; CRUPPERNECK; DOUBLE TOLL GATE; EAST HAGERSTOWN; GLENVILLE; GREENWOOD; NIPETOWN; PARAMOUNT; REDBUD; REID; RINGGOLD; SENECA CAVERNS; SHAFFERS CORNER; SPRINGDALE; WESTON; WILLIAM | 2024-10-08 | Not reported |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-16 | SRRTEP Western Item 01 - APS Supplemental Projects Presentation p. 10 |
New Customer Connection | No role wording 138 kV |
| 2026-10-16 | SRRTEP Western Item 01 - APS Supplemental Projects Presentation p. 9 |
Misoperation Relays | No role wording 138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 102 |
Bedington No. 3 500/138 kV Transformer | “At Bedington Substation: Replace No. 3 500/138 kV transformer with a new 500/138 kV transformer of the same size.” 500/138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 118 |
Misoperation Relay Projects | “At Bedington, replace circuit breaker, disconnect switches, line trap, substation conductor and relaying” 138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 127 |
Misoperation Relay Projects | “replace circuit breakers, disconnect switches, line trap and relaying” 138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 21 |
Marlowe Substation | No role wording 138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 43 |
Bedington – Marlowe BMA 138 kV Line New Customer | “Replace two breakers and relay panels at Bedington Substation” 138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 54 |
Bedington Substation | “The 500/138 kV No. 1 Transformer at Bedington was manufactured 47 years ago and is approaching end of life.” 500/138 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2024 RTEP p. 58 |
Bedington – Doubs 500 kV Misoperation Relays | “Replace circuit breakers, disconnect switches, line trap, substation conductor and relaying at Bedington Substation” 500 kV |
| 2026-09-08* | SRRTEP Western APS local plan submission of the supplemental projects for 2025 RTEP p. 22 |
Bedington – Marlowe 138 kV Line | “At Bedington Substation, replace circuit breakers” 138 kV |
| 2025-11-14 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 9 |
Bedington – Eagle 138 kV | “At Bedington:
• Install foundation, conduit, and grounding for new equipment.” 138 kV |
| 2025-10-17 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 3 |
Bedington – Eagle 138 kV | “At Bedington:” 138 kV |
| 2025-10-08 | TEAC Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 22 |
Bedington – Marlowe 138 kV Line | “At Bedington Substation, replace circuit breakers, disconnect switches” 138 kV |
| 2025-05-16 | SRRTEP Western Item 06 - APS Supplemental Project p. 9 |
Bedington – Marlowe 138 kV Line | “At Bedington Substation, replace circuit breakers” 138 kV |
| 2025-03-14 | SRRTEP Western Item 07 - APS Supplemental Project p. 6 |
Bedington – Marlowe 138 kV Line | No role wording 138 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 102 |
Bedington No. 3 500/138 kV Transformer | “At Bedington Substation:” 500/138 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 118 |
Misoperation Relay Projects | “At Bedington, replace circuit breaker, disconnect switches, line trap, substation conductor and relaying” |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 127 |
Misoperation Relay Projects | “At Bedington, replace circuit breakers, disconnect switches, line trap and relaying.” |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 21 |
Marlowe Substation | No role wording 138 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 43 |
Bedington – Marlowe BMA 138 kV Line New Customer | “Replace two breakers and relay panels at Bedington Substation” 138 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 54 |
Bedington Substation | “The 500/138 kV No. 1 Transformer at Bedington was manufactured 47 years ago” 500/138 kV |
| 2024-10-08 | TEAC Informational Only - APS Local Plan submission of supplemental project 2024 p. 58 |
Bedington – Doubs 500 kV Misoperation Relays | “Replace circuit breakers, disconnect switches, line trap, substation conductor
and relaying at Bedington Substation” 500 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.