Bedington

Named in 9 PJM planning documents for 13 projects, from October 8, 2024 to October 16, 2026.

Existingdescribed as
APSzone
138 kV, 500 kV, 500/138 kVkV as printed
22mentions

Also printed as: Bedington Substation

PJM interconnection queue

A PJM queue substation page has the same name: Bedington (WV) — 2 queue requests filed, 2 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Bedington – Eagle 138 kV
b3976.1
Not printed $1.96M 06/01/2030 Not printed 2025-11-14
SRRTEP Western
Bedington – Eagle 138 kV Not printed $1.96M 06/01/2030 Not printed 2025-10-17
SRRTEP Western
Marlowe Substation
APS-2023-027 · s3131.1
Not printed $ 0.3 M 10/27/2023 Not printed 2024-10-08
TEAC
Bedington Substation
APS-2023-028 · s3162.1
Not printed $21.8M 06/01/2027 Not printed 2024-10-08
TEAC
Bedington – Marlowe BMA 138 kV Line New Customer
APS-2023-030 · s3103.1
Not printed $30.4M 6/30/2026 Not printed 2024-10-08
TEAC
Bedington – Doubs 500 kV Misoperation Relays
APS-2023-057 · s3163.1
Not printed $ 6.95 M 02/28/2025 Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-008, APS-2024-011, APS-2024-013, APS-2024-015, APS-2024-016, APS-2024-024, APS-2024-030 to APS-2024-034 · s3470.1, s3471.1, s3472.1, s3473.1, s3474.1, s3475.1, s3476.1, s3477.1, s3478.1, s3479.1, s3480.1
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-016, APS-2024-024, APS-2024-030, APS-2024-031 · s3474.1, s3475.1, s3476.1, s3477.1
Not printed Not printed Not printed Not printed 2026-09-08*
SRRTEP Western
Bedington No. 3 500/138 kV Transformer
APS-2024-027 · s3452.1
Not printed $18.7M 12/31/2027 Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-039, APS-2024-041 to APS-2024-045, APS-2024-048 to APS-2024-051
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Bedington – Marlowe 138 kV Line
APS-2025-007 · s3667.1
Not printed $4.00M 7/26/2029 Not printed 2025-10-08
TEAC
Misoperation Relays
APS-2026-051
Not printed Not printed Not printed Not printed 2026-10-16
SRRTEP Western
New Customer Connection
APS-2026-078
Not printed Not printed 1/1/2028 approximately 200 MW 2026-10-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 6/30/2026 → 2/28/2025 2024-10-08 Not reported
Substations named ANTIETAM; BEDINGTON; BELMONT; BETHELBORO; CARNEGIE; CHARLEROI; DONEGAL; E HAGERSTOWN; EAST HAGERSTOWN; EDGELAWN; HAMPSHIRE; IRON BRIDGE; MARLOWE; PAPER CITY; RENO TAP; RIDGELEY; RIDGWAY; TIDD; TRISSLER; WEIRTON; YUKON → ANTIETAM; BETHELBORO; CHARLEROI; EAST HAGERSTOWN; PAPER CITY; RIDGWAY; YUKON 2024-10-08 Not reported
Substations named ANTIETAM; BACK FORK; BEDINGTON; CANAAN VALLEY; COWEN; CRUPPERNECK; DOUBLE TOLL GATE; EAST HAGERSTOWN; GLENVILLE; GREENWOOD; NIPETOWN; PARAMOUNT; REDBUD; REID; RINGGOLD; SENECA CAVERNS; SHAFFERS CORNER; SHAFFERS CORNERS; SPRINGDALE; WESTON; WILLIAM → ANTIETAM; BACK FORK; BEDINGTON; CANAAN VALLEY; COWEN; CRUPPERNECK; DOUBLE TOLL GATE; EAST HAGERSTOWN; GLENVILLE; GREENWOOD; NIPETOWN; PARAMOUNT; REDBUD; REID; RINGGOLD; SENECA CAVERNS; SHAFFERS CORNER; SPRINGDALE; WESTON; WILLIAM 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 10
New Customer Connection No role wording
138 kV
2026-10-16 SRRTEP Western
Item 01 - APS Supplemental Projects Presentation p. 9
Misoperation Relays No role wording
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 102
Bedington No. 3 500/138 kV Transformer “At Bedington Substation: Replace No. 3 500/138 kV transformer with a new 500/138 kV transformer of the same size.”
500/138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 118
Misoperation Relay Projects “At Bedington, replace circuit breaker, disconnect switches, line trap, substation conductor and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 127
Misoperation Relay Projects “replace circuit breakers, disconnect switches, line trap and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 21
Marlowe Substation No role wording
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 43
Bedington – Marlowe BMA 138 kV Line New Customer “Replace two breakers and relay panels at Bedington Substation”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 54
Bedington Substation “The 500/138 kV No. 1 Transformer at Bedington was manufactured 47 years ago and is approaching end of life.”
500/138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 58
Bedington – Doubs 500 kV Misoperation Relays “Replace circuit breakers, disconnect switches, line trap, substation conductor and relaying at Bedington Substation”
500 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 22
Bedington – Marlowe 138 kV Line “At Bedington Substation, replace circuit breakers”
138 kV
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 9
Bedington – Eagle 138 kV “At Bedington: • Install foundation, conduit, and grounding for new equipment.”
138 kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 3
Bedington – Eagle 138 kV “At Bedington:”
138 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 22
Bedington – Marlowe 138 kV Line “At Bedington Substation, replace circuit breakers, disconnect switches”
138 kV
2025-05-16 SRRTEP Western
Item 06 - APS Supplemental Project p. 9
Bedington – Marlowe 138 kV Line “At Bedington Substation, replace circuit breakers”
138 kV
2025-03-14 SRRTEP Western
Item 07 - APS Supplemental Project p. 6
Bedington – Marlowe 138 kV Line No role wording
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 102
Bedington No. 3 500/138 kV Transformer “At Bedington Substation:”
500/138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 118
Misoperation Relay Projects “At Bedington, replace circuit breaker, disconnect switches, line trap, substation conductor and relaying”
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 127
Misoperation Relay Projects “At Bedington, replace circuit breakers, disconnect switches, line trap and relaying.”
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 21
Marlowe Substation No role wording
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 43
Bedington – Marlowe BMA 138 kV Line New Customer “Replace two breakers and relay panels at Bedington Substation”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 54
Bedington Substation “The 500/138 kV No. 1 Transformer at Bedington was manufactured 47 years ago”
500/138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 58
Bedington – Doubs 500 kV Misoperation Relays “Replace circuit breakers, disconnect switches, line trap, substation conductor and relaying at Bedington Substation”
500 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.