Marlowe Substation

Named in 6 PJM planning documents for 5 projects, from October 8, 2024 to October 8, 2025.

Existingdescribed as
APSzone
138 kVkV as printed
10mentions

Also printed as: Marlowe

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Marlowe Substation
APS-2023-027 · s3131.1
Not printed $ 0.3 M 10/27/2023 Not printed 2024-10-08
TEAC
Bedington – Marlowe BMA 138 kV Line New Customer
APS-2023-030 · s3103.1
Not printed $30.4M 6/30/2026 Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-008, APS-2024-011, APS-2024-013, APS-2024-015, APS-2024-016, APS-2024-024, APS-2024-030 to APS-2024-034 · s3470.1, s3471.1, s3472.1, s3473.1, s3474.1, s3475.1, s3476.1, s3477.1, s3478.1, s3479.1, s3480.1
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-016, APS-2024-024, APS-2024-030, APS-2024-031 · s3474.1, s3475.1, s3476.1, s3477.1
Not printed Not printed Not printed Not printed 2026-09-08*
SRRTEP Western
Bedington – Marlowe 138 kV Line
APS-2025-007 · s3667.1
Not printed $4.00M 7/26/2029 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 6/30/2026 → 2/28/2025 2024-10-08 Not reported
Substations named ANTIETAM; BEDINGTON; BELMONT; BETHELBORO; CARNEGIE; CHARLEROI; DONEGAL; E HAGERSTOWN; EAST HAGERSTOWN; EDGELAWN; HAMPSHIRE; IRON BRIDGE; MARLOWE; PAPER CITY; RENO TAP; RIDGELEY; RIDGWAY; TIDD; TRISSLER; WEIRTON; YUKON → ANTIETAM; BETHELBORO; CHARLEROI; EAST HAGERSTOWN; PAPER CITY; RIDGWAY; YUKON 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 118
Misoperation Relay Projects “At Marlowe, replace disconnect switches, line trap, substation conductor and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 21
Marlowe Substation “At Marlowe Substation:  On the Boonsboro 138 kV line exit, replace”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 43
Bedington – Marlowe BMA 138 kV Line New Customer “Replace one breaker and relay panel at Marlowe Substation.”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2025 RTEP p. 22
Bedington – Marlowe 138 kV Line “At Marlowe Substation, replace disconnect switches”
138 kV
2025-10-08 TEAC
Informational Only - APS Local Plan Submission of the Supplemental Projects for 2025 p. 22
Bedington – Marlowe 138 kV Line “At Marlowe Substation, replace disconnect switches, substation conductor”
138 kV
2025-05-16 SRRTEP Western
Item 06 - APS Supplemental Project p. 9
Bedington – Marlowe 138 kV Line “At Marlowe Substation, replace disconnect switches”
138 kV
2025-03-14 SRRTEP Western
Item 07 - APS Supplemental Project p. 6
Bedington – Marlowe 138 kV Line No role wording
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 118
Misoperation Relay Projects “At Marlowe, replace disconnect switches, line trap, substation conductor and relaying”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 22
Marlowe Substation “At Marlowe Substation:”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 43
Bedington – Marlowe BMA 138 kV Line New Customer “Replace one breaker and relay panel at Marlowe Substation.”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.