Redbud

Named in 4 PJM planning documents for 4 projects, from October 8, 2024 to November 4, 2025.

Existingdescribed as
APSzone
138 kVkV as printed
6mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
McCanns Rd 138 kV Switching Station
b4001.1
Not printed $23.87 M 6/1/2030 Not printed 2025-11-04
TEAC
Greenwood-Redbud 138 kV New Customer
APS-2023-013 · s3126.1
Not printed $1.6M 05/3/2024 Not printed 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-039, APS-2024-041 to APS-2024-045, APS-2024-048 to APS-2024-051
Not printed Not printed Not printed Not printed 2024-10-08
TEAC
McCanns Rd 138 kV Switching Station
2025-W1-631
Not printed $23.87 M 6/1/2030 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named ANTIETAM; BACK FORK; BEDINGTON; CANAAN VALLEY; COWEN; CRUPPERNECK; DOUBLE TOLL GATE; EAST HAGERSTOWN; GLENVILLE; GREENWOOD; NIPETOWN; PARAMOUNT; REDBUD; REID; RINGGOLD; SENECA CAVERNS; SHAFFERS CORNER; SHAFFERS CORNERS; SPRINGDALE; WESTON; WILLIAM → ANTIETAM; BACK FORK; BEDINGTON; CANAAN VALLEY; COWEN; CRUPPERNECK; DOUBLE TOLL GATE; EAST HAGERSTOWN; GLENVILLE; GREENWOOD; NIPETOWN; PARAMOUNT; REDBUD; REID; RINGGOLD; SENECA CAVERNS; SHAFFERS CORNER; SPRINGDALE; WESTON; WILLIAM 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 127
Misoperation Relay Projects “replace disconnect switches, line trap, substation conductor and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 16
Greenwood-Redbud 138 kV New Customer “Modify line relay settings in Greenwood and Redbud substations”
138 kV
2025-11-04 TEAC
Item 14 - Reliability Analysis Update p. 9
McCanns Rd 138 kV Switching Station “Redbud 138 kV Substation”
138 kV
2025-10-08 TEAC
Item 13 - Reliability Analysis Update p. 8
McCanns Rd 138 kV Switching Station “from Redbud 138 kV Substation”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 127
Misoperation Relay Projects “At Redbud, replace disconnect switches, line trap, substation conductor and relaying.”
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 16
Greenwood-Redbud 138 kV New Customer “Modify line relay settings in Greenwood and Redbud substations”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this