Substation Scout

Strasburg substation interconnection queue

1 active project totaling 250 MW in the PJM queue, plus 3 with terminal status (shown grayed).

Target commercial operation dates as filed run from Dec 2012 to Apr 2031 (4 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing), APS (1 filing).

1active projects
250active MW
4total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1876 Strasburg 138 kV 138 250 Battery Active Oct 2030
AI1-186 Strasburg 138 kV 138 140 Battery Withdrawn Dec 2027
C01-2049 Strasburg 138 kV 138 140 Battery Withdrawn Apr 2031
W2-059 Sight & Sound Theaters 12 1 Other Withdrawn Dec 2012

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Tracked changes at this substation

1 change to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-09-28C01-2049Terminal status140 Active → Withdrawn

Other PJM queue substations in Tuscarawas County, OH

No other substation in Tuscarawas County, OH is named as a point of interconnection in the PJM queue.

All 4 PJM queue filings in Tuscarawas County, OH.

Other PJM queue substations in Shenandoah County, VA

All 11 PJM queue filings in Shenandoah County, VA.

Other PJM queue substations in Lancaster County, PA

All 41 PJM queue filings in Lancaster County, PA.