Substation Scout

Rock Springs-Peach Bottom substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
AA2-109 Rock Springs-Peach Bottom 500kV 500 1,100 Gas Withdrawn
AB1-111 Rock Springs-Peach Bottom 500kV 500 135 Gas Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.