Red Lion
Named in 1 PJM planning document for 1 project, on December 5, 2023.
Same name on other Substation Scout pages
Other sources that print a substation named “Red Lion”. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
Part of a named transmission project: Bramah–High Ridge 500 kV ($708.77M).
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Recommended Solutions to Address Clusters - East B3800.26 –B3800.51 |
Not printed | $708.77 M | 2028-2030 | Not printed | 2023-12-05 TEAC |
Other substations in this project
“Recommended Solutions to Address Clusters - East” also names 13 other substations, with what the most recent document says about each.
- Brighton PJM system-wide Work described at it — “Replace terminal equipment at both Brighton and Waugh Chapel” (p. 53)
- Chalk Point PJM system-wide Work described at it — “Replace relay at Chalk Point 500 kV” (p. 55)
- Cheltanham PJM system-wide Not stated
- Conastone PJM system-wide Work described at it — “Upgrade (2) existing 500 kV breakers at Conastone” (p. 54)
- Gracetone PJM system-wide Not stated
- High Ridge PJM system-wide New — “Build High Ridge 500 kV substation” (p. 52)
- Hope Creek PJM system-wide Not stated
- North Delta PJM system-wide New — “North Delta 500 kV termination for the Rock Springs 500 kV line” (p. 52)
- Peach Bottom PJM system-wide Work described at it — “Peach Bottom 500 kV – Reconfigure and upgrade several terminal/substation equipment at both North and South Peach Bottom 500 kV substations” (p. 52)
- Peach Bottom North PJM system-wide Work described at it — “upgrade several terminal/substation equipment at both North and South Peach Bottom 500 kV substations” (p. 56)
- Peach Bottom South PJM system-wide New — “Build new Peach Bottom South - North Delta 500kV line” (p. 52)
- Rock Springs PJM system-wide Work described at it
- Waugh Chapel PJM system-wide Work described at it — “Replace terminal equipment at both Brighton and Waugh Chapel” (p. 53)
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2023-12-05 | TEAC Item 15 - Reliability Analysis Update 2022 Window 3 p. 56 |
Recommended Solutions to Address Clusters - East | “Replace terminal equipment at Red Lion” 500 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.