Red Lion

Named in 4 PJM planning documents for 1 project, from August 14, 2025 to October 6, 2026.

Existingdescribed as
DPLzone
138kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
DPL-2025-001 Not printed $4.9 million 12/19/2025 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 11/28/2025 → 12/19/2025 2025-09-18 2026-10-06
Status under-construction (Construction) → unknown (Complete) 2025-09-18 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - DPL Local Plan Submission of Supplemental Projects for 2026 p. 3
DPL-2025-001 “Install (2) new 2000A 138 kV breakers on the Red Lion 138kV ring bus”
138kV
2026-10-01* SRRTEP Mid-Atlantic
DPL local plan submission for 2026 RTEP p. 3
DPL-2025-001 “Install (2) new 2000A 138 kV breakers on the Red Lion 138kV ring bus”
138kV
2025-09-18 SRRTEP Mid-Atlantic
Item 04 - DPL Supplemental Projects p. 6
DPL-2025-001 “Install (2) new 2000A 138 kV breakers on the Red Lion 138kV ring bus”
138kV
2025-08-14 SRRTEP Mid-Atlantic
Item 02 - DPL Supplemental Projects p. 3
DPL-2025-001 “existing distribution facilities do not have the capacity to support this growing demand. Additionally, Red Lion substation has only a single distribution transformer”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.