Maddox Creek substation interconnection queue
3 active projects totaling 113.2 MW in the PJM queue, plus 1 with terminal status (shown grayed).
4 PJM queue filings name Maddox Creek as the point of interconnection, all in Van Wert County, OH.
Target commercial operation dates as filed run from Dec 2019 to Dec 2027 (4 filings). 3 active filings target a date after November 27, 2026.
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF2-014 | Wild Grains Solar | 345 | 90 | Solar | Under Construction | Dec 2027 |
| AE1-102 | Blue Creek Wind Farm | 345 | 15.6 | Solar | Engineering and Procurement | Sep 2027 |
| AB2-016 | Maddox Creek 345kV | 345 | 13 | Wind | Withdrawn | Dec 2019 |
| AC2-044 | Blue Creek Wind Farm | 345 | 7.6 | Solar | Engineering and Procurement | Sep 2027 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Same name on other Substation Scout pages
Other sources that print a substation named “Maddox Creek” in OH. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each.
- Maddox Creek: Expansion Tracker, PJM planning: AEP (OH)
Other PJM queue substations in Van Wert County, OH
- Maddox Creek-RP Mone: 2 active, 280 MW of 4 filed
- Convoy-East Lima: 1 active, 70 MW of 2 filed
- Southwest Lima: none active of 6 filed
- Marysville-Sorenson: none active of 5 filed
- Haviland – Cavett Switch: none active of 3 filed
- Cavett Switch - West Van Wert: none active of 2 filed