Maddox Creek substation interconnection queue

3 active projects totalling 113.2 MW in the PJM queue, plus 1 with terminal status (shown greyed).

3active projects
113.2active MW
4total filed
Queue IDProjectkVMWResourceStatus
AF2-014 Wild Grains Solar 345 90 Solar Under Construction
AE1-102 Blue Creek Wind Farm 345 15.6 Solar Engineering and Procurement
AB2-016 Maddox Creek 345kV 345 13 Wind Withdrawn
AC2-044 Blue Creek Wind Farm 345 7.6 Solar Engineering and Procurement