Sunbury-Dalmatia substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Sunbury-Dalmatia as the point of interconnection, all in Northumberland County, PA.

Target commercial operation date as filed: Apr 2028 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG1-259 Boyles Run Solar 69 6.7 Solar Withdrawn Apr 2028
AG1-260 Boyles Run Solar 69 6.7 Solar Withdrawn Apr 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Tracked changes at this substation

2 changes to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-10-12AG1-259Status changen/a Pending Termination → Withdrawn
2026-10-12AG1-260Status changen/a Pending Termination → Withdrawn

Other PJM queue substations in Northumberland County, PA

All 36 PJM queue filings in Northumberland County, PA.