Cottontail Solar 4 aka East Chilli Solar
PJM queue ID AE2-059
Cottontail Solar 4 aka East Chilli Solar (AE2-059) is listed in the PJM interconnection queue as a 8.4 MW solar project in Northumberland County, PA. The filing names Derry Tap-Derry Bus as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of May 31, 2024.
| Queue ID | AE2-059 |
|---|---|
| Project name | Cottontail Solar 4 aka East Chilli Solar |
| Status (as published) | In Service |
| Substation | Derry Tap-Derry Bus |
| Point of interconnection | Derry Tap-Derry Bus 69 kV |
| County | Northumberland |
| State | PA |
| Voltage | 69 kV |
| Capacity | 8.4 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2024-05-31 |
| Source dataset | serial |
Same substation and county
Derry Tap-Derry Bus substation: 2 requests in the PJM queue, 1 active totaling 8.4 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AE2-084 | Cottontail Solar 3 | 8.4 | Solar | Withdrawn |
Northumberland, PA: 36 requests in the PJM queue, 7 active totaling 129.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 20 |
| MW capacity | 8.4 |
| MFO | 20 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.