Clinton-Stuart substation interconnection queue
1 active project totalling 180 MW in the PJM queue, plus 3 with terminal status (shown greyed).
1active projects
180active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AE2-221 | Yellow Wood Solar Energy Center | 345 | 180 | Solar | Under Construction |
| AF1-034 | Clinton-Stuart 345 kV | 345 | 180 | Solar | Withdrawn |
| AF2-113 | Clinton-Stuart 345 kV | 345 | 75 | Battery | Withdrawn |
| AF1-035 | Clinton-Stuart 345 kV | 345 | 60 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.