Hillsboro-Middleboro substation interconnection queue

2 active projects totalling 110.7 MW in the PJM queue.

2active projects
110.7active MW
2total filed
Queue IDProjectkVMWResourceStatus
AG1-107 Palomino Solar 138 85.7 Solar Under Construction
AF2-440 Palomino Solar 138 25 Solar Under Construction

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.