Pierce - Kyger Creek substation interconnection queue

2 active projects totalling 217.9 MW in the PJM queue, plus 2 with terminal status (shown greyed).

2active projects
217.9active MW
4total filed
Queue IDProjectkVMWResourceStatus
C01-1343 Pierce - Kyger Creek 345 kV 345 200 Battery Active
AI2-085 Pierce - Kyger Creek 345 kV 345 65 Solar Withdrawn
AH1-404 Pierce - Kyger Creek 345 kV 345 24 Solar Withdrawn
AH1-537 Pierce - Kyger Creek 345 kV 345 17.9 Solar Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.