Hillsboro substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 10 with terminal status (shown grayed).
Target commercial operation dates as filed run from Jun 2019 to Apr 2029 (10 filings).
0active projects
0active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AC2-042 | Hillsboro 138kV | 138 | 120 | Solar | Withdrawn | Jun 2019 |
| AD2-010 | Hillsboro 138 kV | 138 | 120 | Solar | Withdrawn | Jun 2019 |
| AC1-157 | Hillsboro 138kV | 138 | 100 | Solar | Withdrawn | Oct 2019 |
| AC2-031 | Hillsboro 138kV | 138 | 67 | Solar | Withdrawn | Oct 2019 |
| AC2-041 | Hillsboro 138kV | 138 | 60 | Solar | Withdrawn | Jun 2019 |
| AD2-011 | Hillsboro 138 kV | 138 | 60 | Solar | Withdrawn | Jun 2019 |
| AC1-144 | Hillsboro 138kV | 138 | 57.2 | Solar | Withdrawn | Oct 2019 |
| AI1-133 | Hillsboro 69 kV | 69 | 50 | Hybrid | Withdrawn | Apr 2029 |
| AC2-040 | Hillsboro 138kV | 138 | 29.4 | Solar | Withdrawn | Jun 2019 |
| AD2-012 | Hillsboro 138 kV | 138 | 29.4 | Solar | Withdrawn | Jun 2019 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Highland County, OH
- Stuart-Clinton: 3 active, 290 MW of 3 filed
- Pierce - Kyger Creek: 1 active, 200 MW of 4 filed
- Clinton-Stuart: 1 active, 180 MW of 4 filed
- Hillsboro-Middleboro: 2 active, 110.7 MW of 2 filed
- Buckskin: 2 active, 77.2 MW of 10 filed
- Hillsboro-Wildcat: 1 active, 57 MW of 2 filed
- Highland: none active of 4 filed
- Buckskin – Worley: none active of 2 filed
- Hillsboro-Millbrook: none active of 2 filed
- Stuart - Clinton: none active of 2 filed
- Wildcat: none active of 2 filed
Other PJM queue substations in Fleming County, KY
- Flemingsburg - Spurlock: 1 active, 48 MW of 3 filed
- Flemingsburg: 1 active, 0 MW of 2 filed