Highland, OH interconnection queue
9 active projects totalling 875.6 MW in the PJM queue, plus 31 with terminal status (shown greyed).
9active projects
875.6active MW
40total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-766 | Not reported | n/r | 205 | Battery | Withdrawn |
| C01-1343 | Pierce - Kyger Creek 345 kV | 345 | 200 | Battery | Active |
| C01-1749 | HILLSBORO - HIGHLAND 138 kV | 138 | 200 | Battery | Active |
| AF1-034 | Clinton-Stuart 345 kV | 345 | 180 | Solar | Withdrawn |
| AC1-085 | Highland County Solar | 345 | 152 | Solar | In Service |
| C01-2215 | Stuart - Clinton 345 kV | 345 | 136.6 | Solar | Withdrawn |
| AC2-042 | Hillsboro 138kV | 138 | 120 | Solar | Withdrawn |
| AD2-010 | Hillsboro 138 kV | 138 | 120 | Solar | Withdrawn |
| AC1-157 | Hillsboro 138kV | 138 | 100 | Solar | Withdrawn |
| AI2-447 | Hillsboro-Wildcat 138kV | 138 | 87.3 | Solar | Withdrawn |
| AG1-107 | Palomino Solar | 138 | 85.7 | Solar | Under Construction |
| AF1-283 | Highland 3 Solar | 345 | 78 | Solar | Engineering and Procurement |
| AC2-064 | Hillsboro-Millbrook 138kV | 138 | 69 | Solar | Withdrawn |
| AC2-031 | Hillsboro 138kV | 138 | 67 | Solar | Withdrawn |
| AI2-085 | Pierce - Kyger Creek 345 kV | 345 | 65 | Solar | Withdrawn |
| AC2-041 | Hillsboro 138kV | 138 | 60 | Solar | Withdrawn |
| AD2-011 | Hillsboro 138 kV | 138 | 60 | Solar | Withdrawn |
| AF1-035 | Clinton-Stuart 345 kV | 345 | 60 | Solar | Withdrawn |
| AF1-282 | Nuthatch Solar 5 | 345 | 60 | Solar | Engineering and Procurement |
| AC1-144 | Hillsboro 138kV | 138 | 57.2 | Solar | Withdrawn |
| AC1-089 | Willowbrook Solar | 138 | 57 | Solar | In Service |
| AF2-124 | Kyger Creek-Pierce 345 kV | 345 | 50.4 | Solar | Withdrawn |
| C01-2219 | Stuart - Clinton 345 kV | 345 | 47.1 | Hybrid | Withdrawn |
| C01-2220 | Clay Substation 345 kV | 345 | 36.2 | Hybrid | Withdrawn |
| AG1-456 | Wildcat 138 kV | 138 | 30 | Battery | Withdrawn |
| AC2-040 | Hillsboro 138kV | 138 | 29.4 | Solar | Withdrawn |
| AC2-049 | Hillsboro-Millbrook 138kV | 138 | 29.4 | Solar | Withdrawn |
| AD2-012 | Hillsboro 138 kV | 138 | 29.4 | Solar | Withdrawn |
| AH2-159 | Buckskin – Worley 69 kV | 69 | 29.4 | Solar | Withdrawn |
| AF2-440 | Palomino Solar | 138 | 25 | Solar | Under Construction |
| AH1-404 | Pierce - Kyger Creek 345 kV | 345 | 24 | Solar | Withdrawn |
| AG2-194 | Pierce-Kyger Creek 345 kV | 345 | 21 | Solar | Withdrawn |
| AC2-055 | Buckskin 69kV | 69 | 18.1 | Solar | Withdrawn |
| AH1-537 | Pierce - Kyger Creek 345 kV | 345 | 17.9 | Solar | Active |
| AH2-160 | Buckskin – Worley 69 kV | 69 | 12 | Solar | Withdrawn |
| AC2-019 | Highland 12kV | 12 | 3.8 | Solar | Withdrawn |
| AC2-028 | Highland 13.2kV | 13.2 | 3.8 | Solar | Withdrawn |
| V1-032 | Highland 69kV | 69 | 1.9 | Solar | Withdrawn |
| AC2-008 | Wildcat 12kV | 12 | 0 | Solar | Withdrawn |
| AC2-027 | Highland 12kV | 12 | 0 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.