Substation Scout

John Day substation substation interconnection queue

1 active project totalling 201 MW in the BPA queue, plus 3 with terminal status (shown greyed).

1active projects
201active MW
4total filed
Queue IDProjectkVMWResourceStatus
G0946 Not reported 500 650 Battery WITHDRAWN
G0947 Not reported 500 650 Battery WITHDRAWN
G0948 Not reported 500 650 Battery WITHDRAWN
G0223 Hay Canyon/Star Point n/r 201 Wind ENERGIZED

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.