Buckley Substation at substation interconnection queue

1 active project totalling 277 MW in the BPA queue, plus 1 with terminal status (shown greyed).

1active projects
277active MW
2total filed
Queue IDProjectkVMWResourceStatus
G0995 Not reported 500 400 Wind WITHDRAWN
G0994 Not reported 500 277 Wind STUDY

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.