Sherman, OR interconnection queue
27 active projects totalling 7,080 MW in the BPA queue, plus 31 with terminal status (shown greyed).
27active projects
7,080active MW
58total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| G0759 | Not reported | 500 | 1,650 | Solar | WITHDRAWN |
| G0983 | Not reported | 500 | 1,200 | Solar | WITHDRAWN |
| G0687 | Not reported | n/r | 900 | Solar | STUDY |
| G0615 | Not reported | 500 | 800 | Solar | E&P EXECUTED |
| G0791 | Not reported | 500 | 650 | Solar | STUDY |
| G0792 | Not reported | 500 | 650 | Battery | WITHDRAWN |
| G0795 | Not reported | 500 | 650 | Solar | WITHDRAWN |
| G0796 | Not reported | 500 | 650 | Battery | WITHDRAWN |
| G0946 | Not reported | 500 | 650 | Battery | WITHDRAWN |
| G0947 | Not reported | 500 | 650 | Battery | WITHDRAWN |
| G0948 | Not reported | 500 | 650 | Battery | WITHDRAWN |
| G0614 | Not reported | 500 | 600 | Solar | WITHDRAWN |
| G99 | Biglow Canyon Wind | n/r | 600 | Wind | ENERGIZED |
| G0864 | Not reported | 500 | 500 | Battery | STUDY |
| G0874 | Not reported | n/r | 500 | Solar | WITHDRAWN |
| G0931 | Not reported | n/r | 500 | Solar | WITHDRAWN |
| G1041 | Not reported | 500 | 500 | Wind | WITHDRAWN |
| G0344 | Not reported | 500 | 488 | Wind | E&P EXECUTED |
| G0712 | Not reported | n/r | 448 | Solar | STUDY |
| G0751 | Not reported | 500 | 412.5 | Battery | WITHDRAWN |
| G0850 | Not reported | 500 | 400 | Solar | STUDY |
| G0851 | Not reported | 500 | 400 | Solar | WITHDRAWN |
| G0995 | Not reported | 500 | 400 | Wind | WITHDRAWN |
| G0323 | Not reported | 500 | 300 | Wind | WITHDRAWN |
| G0711 | Not reported | n/r | 300 | Solar | STUDY |
| G0866 | Not reported | n/r | 300 | Solar | STUDY |
| G0981 | Not reported | 500 | 300 | Wind | WITHDRAWN |
| G0982 | Not reported | 500 | 300 | Wind | WITHDRAWN |
| G1042 | Not reported | 500 | 300 | Battery | WITHDRAWN |
| G0994 | Not reported | 500 | 277 | Wind | STUDY |
| G0989 | Not reported | 230 | 275 | Solar | WITHDRAWN |
| G113 | RES North America LLC | n/r | 250 | Wind | WITHDRAWN |
| G0280 | Not reported | n/r | 242 | Wind | WITHDRAWN |
| G0728 | Not reported | 230 | 210 | Wind | WITHDRAWN |
| G0223 | Hay Canyon/Star Point | n/r | 201 | Wind | ENERGIZED |
| G0235 | Not reported | 500 | 200 | Wind | WITHDRAWN |
| G0263 | Not reported | n/r | 200 | Wind | WITHDRAWN |
| G0714 | Not reported | 500 | 200 | Solar | STUDY |
| G0715 | Not reported | 500 | 200 | Solar | STUDY |
| G0865 | Not reported | n/r | 200 | Solar | STUDY |
| G1002 | Not reported | 500 | 200 | Solar | STUDY |
| G0980 | Not reported | 500 | 191 | Wind | STUDY |
| G0402 | Not reported | n/r | 110 | Wind | WITHDRAWN |
| G0279 | Not reported | n/r | 105 | Wind | WITHDRAWN |
| G57 | GNA Energy | 115 | 105 | Wind | WITHDRAWN |
| G0237 | Not reported | 500 | 100 | Wind | WITHDRAWN |
| G0867 | Not reported | n/r | 100 | Wind | STUDY |
| G0719 | Not reported | n/r | 80 | Solar | WITHDRAWN |
| G0297 | Biglow Canyon Wind Farm Addition | n/r | 50 | Wind | ENERGIZED |
| G0283 | Not reported | n/r | 40 | Wind | WITHDRAWN |
| G0827 | G0827 Klondike Wind | 230 | 25 | Wind | ENERGIZED |
| G54 | Klondike Wind Power | 69 | 24 | Wind | ENERGIZED |
| G0516 | Not reported | 230 | 20 | Solar | IA EXECUTED |
| G0618 | Klondike II Repower | 230 | 6 | Wind | ENERGIZED |
| G0617 | Not reported | 230 | 0 | Solar | STUDY COMPLETED |
| G0862 | Not reported | 500 | 0 | Battery | STUDY |
| G0863 | Not reported | 500 | 0 | Battery | STUDY |
| G0978 | Not reported | 230 | 0 | Solar | STUDY |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with BPA before relying on these figures.