Lackawanna substation interconnection queue
4 active projects totaling 1,436 MW in the PJM queue, plus 3 with terminal status (shown grayed).
7 PJM queue filings name Lackawanna as the point of interconnection, all in Lackawanna County, PA.
Target commercial operation dates as filed run from Jun 2004 to Dec 2029 (7 filings). 1 active filing targets a date after November 27, 2026.
Transmission owner as filed: PPL (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| X4-048 | Lackawanna Thermal Generating Station | 230 | 1,000 | Gas | In Service | Dec 2018 |
| B45 | Lackawanna 230kV | 230 | 555 | Gas | Withdrawn | Jun 2004 |
| AB1-108 | Lackawanna 500 kV | 500 | 485 | Gas | Withdrawn | Jun 2019 |
| Y2-089 | Lackawanna Thermal Generating Station | 230 | 370 | Gas | In Service | Apr 2019 |
| AH1-697 | Lackawanna 230kV | 230 | 78.6 | Gas | Withdrawn | May 2028 |
| AA1-077 | Lackawanna Thermal Generating Station | 230 | 34 | Gas | In Service | Apr 2019 |
| C01-1170 | Lackawanna 230 kV | 230 | 32 | Gas | Active | Dec 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
PJM planning mentions
A substation with the same name is named in PJM transmission planning materials: Lackawanna (PPL, 20 mentions).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Other PJM queue substations in Lackawanna County, PA
- Lackawanna - Hopatcong: 3 active, 3,454.2 MW of 3 filed
- Greenfield: 1 active, 31.6 MW of 3 filed
- Milan: 2 active, 21 MW of 4 filed
- Peckville: 1 active, 1 MW of 2 filed
- Peckville-Jackson: none active of 4 filed