Brookside

Named in 2 PJM planning documents for 1 project, on October 6, 2026.

Not stateddescribed as
PPLzone
69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Tinker Tap Strengthening
PPL-2026-0017
Conceptual $34.6 M 11/30/2029 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named ELK MOUNTAIN; TINKER → ELK MOUNTAIN; GREENFIELD; TINKER 2026-03-18 2026-04-14
Substations named ELK MOUNTAIN; GREENFIELD; TINKER → BROOKSIDE; ELK MOUNTAIN; GREENFIELD; LACKAWANNA; TINKER 2026-04-14 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 93
Tinker Tap Strengthening No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 93
Tinker Tap Strengthening No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.