Mowry

Named in 2 PJM planning documents for 1 project, on October 6, 2026.

Not stateddescribed as
PPLzone
69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Fountain Springs, PA
PPL-2025-0028
Conceptual $1.6 M 11/30/2028 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 11/2028 → 11/30/2028 2025-12-11 2026-02-12
Substations named FOUNTAIN SPRINGS → FOUNTAIN SPRINGS; FOUNTAIN SPRINGS CREEK; FRACKVILLE 2025-12-11 2026-02-12
Substations named FOUNTAIN SPRINGS; FOUNTAIN SPRINGS CREEK; FRACKVILLE → FOUNTAIN SPRINGS; FOUNTAIN SPRINGS CREEK; FRACKVILLE; MOWRY 2026-02-12 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 39
Fountain Springs, PA No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 39
Fountain Springs, PA No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.