Greenwood

Named in 2 PJM planning documents for 1 project, on October 6, 2026.

Not stateddescribed as
PPLzone
69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Frackville, PA
PPL-2019-0004
Conceptual $45 M 06/30/2028 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 5
Frackville, PA No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 5
Frackville, PA No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.