Doyle
Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GTCproject sponsor
2projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: EAST WALTON 500/230kV PROJECT GTC: - Construct the East Walton 500/230kV substation - Construct the Bostwick 230kV switching station - Construct the East Walton - Rockville 500kV line - Construct the Bethabara - East Walton 230kV line - Construct the Bostwick - East Walton 230kV line - Construct the East Walton - Jack's Creek 230kV line - At Bethabara, terminate the East Walton 230kV line - Loop the East Social Circle - East Watkinsville 230kV li… TEAMS 09662 · plan p.130 · zone 212 |
GTC | In the plan p.10 |
Jun 1, 2027 | No change | Bethabara, Bostwick, Doyle, East Social Circle, East Walton, East Watkinsville, Jack's Creek, LG&E Monroe, Rockville, Scherer, Warthen |
| GTC: DOYLE - WINDER PRIMARY 230kV LINE JUMPER REPLACEMENT Replace the limiting jumper with higher rated equipment at Doyle on the Doyle - Winder Primary 230kV line. TEAMS 20778 · plan p.128 · zone 212 |
GTC | In the plan p.10 |
Jun 1, 2027 | No change | Doyle, Winder Primary |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.