Rockville

Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
500kV in the quote
GTCproject sponsor
1projects in the plan

Described as new. The quoted wording describes building this substation, without the word "new". “Construct the Rockville 500kV switching station” — TEAMS 09662, plan p.130

The plan prints no county for this substation, and no utility project page found names one for it.

Location

33.3278, -83.1860 · Putnam County, GA · view on a map

Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±75 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Symbol anchored: the drawn switching-station footprint (grey stippled rectangle labelled "Proposed Rockville 500 kV Switching Station") on the EA's Figure 8.0 site plan. Rendered at 220 dpi (~1.0 m/px by its scale bar). Affine fit on seven towers drawn as white squares on the existing Eatonton Primary #2 - Wallace Dam 230 kV line (3) and Scherer - Warthen 500 kV line (4), each matched to a vertex of the OSM line (230 kV way 171527959; 500 kV way 164024561 'Warthen - Scherer 500kV'); residuals 0.3-1.3 m, fitted scale 1.00/1.01 m/px. Point is the footprint centre, on the east side of the triangular GPC tract west of Rockville Road. ±75 m.

Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.130 · 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.252 · Environmental Assessment: East Central Georgia Reliability Projects (USDA Rural Utilities Service for Georgia Transmission; re-published by DOE as DOE/EA-2313), Rockville site plan (April 2025 (DOE re-publication March 2026)), p.ii · DOE/EA-2313 adoption cover sheet, Rockville 500kV Substation project (Georgia Power, Energy Dominance Financing) (2026-03-24), p. 1-2 · OpenStreetMap: Scherer - Warthen 500 kV and Eatonton Primary #2 - Wallace Dam 230 kV lines, Rockville Road (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GTC: EAST WALTON 500/230kV PROJECT
GTC: - Construct the East Walton 500/230kV substation - Construct the Bostwick 230kV switching station - Construct the East Walton - Rockville 500kV line - Construct the Bethabara - East Walton 230kV line - Construct the Bostwick - East Walton 230kV line - Construct the East Walton - Jack's Creek 230kV line - At Bethabara, terminate the East Walton 230kV line - Loop the East Social Circle - East Watkinsville 230kV li…
TEAMS 09662 · plan p.130 · zone 212
GTC In the plan
p.10
Jun 1, 2027 No change Bethabara, Bostwick, Doyle, East Social Circle, East Walton, East Watkinsville, Jack's Creek, LG&E Monroe, Rockville, Scherer, Warthen

Generation interconnection requests filed in Putnam, GA: Southern Company queue, 2 active of 13. Same county, not the same substation.

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.