East Social Circle
Named in 4 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
4projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: EAST WALTON 500/230kV PROJECT GTC: - Construct the East Walton 500/230kV substation - Construct the Bostwick 230kV switching station - Construct the East Walton - Rockville 500kV line - Construct the Bethabara - East Walton 230kV line - Construct the Bostwick - East Walton 230kV line - Construct the East Walton - Jack's Creek 230kV line - At Bethabara, terminate the East Walton 230kV line - Loop the East Social Circle - East Watkinsville 230kV li… TEAMS 09662 · plan p.130 · zone 212 |
GTC | In the plan p.10 |
Jun 1, 2027 | No change | Bethabara, Bostwick, Doyle, East Social Circle, East Walton, East Watkinsville, Jack's Creek, LG&E Monroe, Rockville, Scherer, Warthen |
| GTC: EAST SOCIAL CIRCLE - SNELLVILLE 230kV EQUIPMENT UPGRADE Replace limiting elements on the East Social Circle - Snellville 230kV line with higher rated equipment. TEAMS 12147 · plan p.294 · zone 212 |
GTC | In the plan p.22 |
Jun 1, 2033 | No change | East Social Circle, Snellville |
| GTC: BOSTWICK - EAST SOCIAL CIRCLE 230kV RECONDUCTOR Reconductor approximately 10.8 miles of the East Social Circle - East Watkinsville 230kV line from 1033 ACSR Curlew conductor to 1033 ACCR 200C conductor. TEAMS 19992 · plan p.163 · zone 212 |
GTC | In the plan p.13 |
Jun 1, 2028 | No change | Bostwick, East Social Circle, East Watkinsville |
| CC: NORTH SPA 230kV (NETWORK IMPROVEMENTS) This project includes the following scope of work: Build a new 230kV switching station north of Oasis with 4 - breakers. Loop in the East Social Circle - Oasis (White) 230kV line. Build new Alcovy Trestle 230kV switching Station. Build new 7 miles, 230kV line from North Spa to Alcovy Trestle with (2) 200C 1351 ACSS. Build new 6 miles, 230kV line from Morning Hornet to Alcovy Trestle with (2) 200C 1351 ACSS. Build (2)… TEAMS 21093 · plan p.144 · zone 214 |
GPC | In the plan p.11 |
Jun 1, 2027 | Advanced from 2030 to 2027 | East Social Circle, Oasis |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner