Jack's Creek

Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
230kV in the quote
GTCproject sponsor
1projects in the plan

Described as new. The quoted wording describes building this substation, without the word "new". “Construct the Jack's Creek 230kV switching station” — TEAMS 09662, plan p.130

The plan prints no county for this substation, and no utility project page found names one for it.

Location

33.8202, -83.6926 · Walton County, GA · view on a map

Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±100 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: Symbol anchored: the drawn switching-station footprint (grey stippled polygon labelled "Proposed Jacks Creek 230 kV Switching Station") on the EA's Figure 7.0 site plan. Rendered at 220 dpi (~1.0 m/px by its scale bar). Affine fit on four OSM anchors: the existing Doyle - Monroe 230 kV and 115 kV lines where each crosses Old Athens Highway (33.818706,-83.692801; 33.818789,-83.692581), Jacks Creek's crossing of Gratis Road (33.823127,-83.699445) and the Monroe #3 (MEAG) 115 kV substation drawn on the plan (OSM 'Monroe #3 (Old Athens Hwy) Substation'); residuals ≤1 m, fitted scale 0.97/1.03 m/px. Point is the footprint centre, just east of the existing lines and north of Old Athens Highway. ±100 m.

Note: Spelling: the plan prints "Jack's Creek"; Georgia Transmission and the EA print "Jacks Creek" (same station: MEAG-owned, GTC-built, the western terminus of the East Walton line).

Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.130 · Environmental Assessment: East Central Georgia Reliability Projects (USDA Rural Utilities Service for Georgia Transmission; re-published by DOE as DOE/EA-2313), Jacks Creek site plan (April 2025 (DOE re-publication March 2026)), p.ii · Georgia Transmission, East Central Reliability Projects page (with project map east_walton_handout_w_tl_labels.png and mailer map All_Proj_Mailout.png) (n/a (retrieved 2026-11-20)), project descriptions; maps · OpenStreetMap: Doyle - Monroe 230/115 kV lines, Old Athens Highway, Gratis Road, Jacks Creek, Monroe #3 substation (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GTC: EAST WALTON 500/230kV PROJECT
GTC: - Construct the East Walton 500/230kV substation - Construct the Bostwick 230kV switching station - Construct the East Walton - Rockville 500kV line - Construct the Bethabara - East Walton 230kV line - Construct the Bostwick - East Walton 230kV line - Construct the East Walton - Jack's Creek 230kV line - At Bethabara, terminate the East Walton 230kV line - Loop the East Social Circle - East Watkinsville 230kV li…
TEAMS 09662 · plan p.130 · zone 212
GTC In the plan
p.10
Jun 1, 2027 No change Bethabara, Bostwick, Doyle, East Social Circle, East Walton, East Watkinsville, Jack's Creek, LG&E Monroe, Rockville, Scherer, Warthen

Generation interconnection requests filed in Walton, GA: Southern Company queue, 0 active of 1. Same county, not the same substation.

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.