Deer Creek
Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).
Described as new. The quoted wording describes building this substation, without the word "new". “Build a 500/230kV station (Deer Creek)” — TEAMS 21419, plan p.156
The plan prints no county for this substation, and no utility project page found names one for it.
Location
On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Sources: 2025 GA ITS Ten-Year Plan (2026-2035), Southern Company Services; filed by Georgia Power in GA PSC Docket 56002 (2025 Annual Transmission Update, public disclosure) (filed 2026-02-27), p.156 · SERTP 2025 Regional Transmission Plan, SOUTHERN Balancing Authority Area project list (2025), p.98 · SERTP Q4 2025 annual transmission planning summit, SOUTHERN BAA project slides (2025-12), slide p.86 · OpenStreetMap: Bonaire Primary and Scherer substations; Bonaire - Scherer 500kV line (way 9424299) (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| CC - DEER CREEK 500/230kV SOLUTION (NETWORK IMPROVEMENTS) Build a 500/230kV station (Deer Creek) splitting the Bonaire Primary - Scherer 500kV line. Install two 500/230kV auto transformers and build 2 bundled 200C 1351 ACSS Martin 230kV lines from Deer Creek to Little Deer Creek. TEAMS 21419 · plan p.156 · zone 214 |
GPC | In the plan p.12 |
Jun 1, 2028 | New project | Bonaire Primary, Deer Creek, Scherer |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.