Rawlings

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.

Not stateddescribed as
DOMzone
—kV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Tunstall 230kV Delivery - DEV
DOM-2022-0028 · s3022
Engineering $140.0M 08/01/2025 77.0 MW 2024-10-08
TEAC
Dominion Transmission Zone: Supplemental Do No Harm Analysis
DOM-2024-0036-DNH (Update)
Conceptual $212M Q4 2031 Not printed 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 14 - DOM Supplemental Projects - Presentation p. 5
Dominion Transmission Zone: Supplemental Do No Harm Analysis No role wording
2026-09-08* SRRTEP Southern
Dominion p. 37
Tunstall 230kV Delivery - DEV No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 37
Tunstall 230kV Delivery - DEV No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.