Guilford

Named in 2 PJM planning documents for 4 projects, on October 8, 2024.

Existingdescribed as
APSzone
138 kVkV as printed
6mentions

Also printed as: Guilford Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Misoperation Relay Projects
APS-2023-023, APS-2023-024, APS-2023-025
Not printed $3.2 M 11/17/2023 Not printed 2026-09-08*
SRRTEP Western
Misoperation Relay Projects
APS-2023-024 · s3101.1
Not printed $2.8 M 05/15/2024 Not printed 2024-10-08
TEAC
Grand Point – Guilford 138 kV Line Customer Connection
APS-2024-035 · s3481.1
Not printed $1.75M 10/31/2025 9 MW 2024-10-08
TEAC
Misoperation Relay Projects
APS-2024-062 to APS-2024-068
Not printed Not printed Not printed Not printed 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named PARKERSBURG; TRISSLER → GARRETT; GUILFORD; PARKERSBURG; REID; RIDGELEY; TRISSLER 2024-10-08 Not reported
Substations named GRAND POINT; GRANDPOINT; GUILFORD → GRANDPOINT; GUILFORD 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 120
Grand Point – Guilford 138 kV Line Customer Connection “The request is approximately four miles from Guilford Substation.”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 132
Misoperation Relay Projects “replace circuit breaker, disconnect switches, substation conductor, line trap and relaying”
138 kV
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 41
Misoperation Relay Projects “At Guilford Substation, replace circuit breaker, wave trap, disconnect switch, substation conductor, & relaying”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 121
Grand Point – Guilford 138 kV Line Customer Connection “Modify line relay settings in Grandpoint and Guilford substations”
138 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 132
Misoperation Relay Projects “At Guilford, replace circuit breaker, disconnect switches, substation conductor, line trap and relaying”
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 41
Misoperation Relay Projects “At Guilford Substation, replace circuit breaker, wave trap, disconnect switch, substation conductor, & relaying”
138 kV