Substation Scout

Winterpock substation interconnection queue

3 active projects totalling 44.5 MW in the PJM queue.

3active projects
44.5active MW
3total filed
Queue IDProjectkVMWResourceStatus
AH1-106 360 Solar Center, LLC 34.5 15.6 Solar Active
AH1-107 360 Solar Center, LLC 34.5 15.6 Solar Active
AE1-074 Winterpock I 34.5 13.3 Solar Partially in Service - Under Construction

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.