Substation Scout

Tyler substation interconnection queue

1 active project totaling 12 MW in the PJM queue, plus 4 with terminal status (shown grayed).

5 PJM queue filings name Tyler as the point of interconnection, all in Chesterfield County, VA.

Target commercial operation dates as filed run from Dec 2022 to Jun 2027 (5 filings). 1 active filing targets a date after November 27, 2026.

1active projects
12active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
AG2-276 Tyler 230 kV 230 150 Battery Withdrawn Dec 2023
AE2-228 Bradley BridgeSolar 34 12 Solar Withdrawn Mar 2025
AF1-291 Chester Solar Technology Park 34.5 12 Solar Engineering and Procurement Jun 2027
AF2-256 Bradley Bridge Solar 34.5 3 Solar Withdrawn Nov 2023
AF2-257 Tyler 34.5 kV 34.5 3 Solar Withdrawn Dec 2022

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Same name on other Substation Scout pages

Other sources that print a substation named “Tyler” in VA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.

Other PJM queue substations in Chesterfield County, VA

All 41 PJM queue filings in Chesterfield County, VA.