Substation Scout

360 Solar Center, LLC

PJM queue ID AH1-106

Queue IDAH1-106
Project name360 Solar Center, LLC
Status (as published)Active
SubstationWinterpock
Point of interconnectionWinterpock 34.5kV
CountyChesterfield
StateVA
Voltage34.5 kV
Capacity15.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operationNot reported
Source datasetcycle

Additional filed fields

Developer360 Solar Center, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC2
StagePHASE 2
Mw Energy26.0
Mw Capacity15.6
Mfo26.0
Submitted Date8/4/2021
Last Updated5/14/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.