360 Solar Center, LLC
PJM queue ID AH1-107
360 Solar Center, LLC (AH1-107) is listed in the PJM interconnection queue as a 15.6 MW solar project in Chesterfield County, VA. The filing names Winterpock as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of October 31, 2027.
| Queue ID | AH1-107 |
|---|---|
| Project name | 360 Solar Center, LLC |
| Status (as published) | Active |
| Substation | Winterpock |
| Point of interconnection | Winterpock 34.5kV |
| County | Chesterfield |
| State | VA |
| Voltage | 34.5 kV |
| Capacity | 15.6 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-10-31 |
| Source dataset | cycle |
Same substation and county
Winterpock substation: 3 requests in the PJM queue, 3 active totaling 44.5 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AH1-106 | 360 Solar Center, LLC | 15.6 | Solar | Active |
| AE1-074 | Winterpock I | 13.3 | Solar | In Service |
Chesterfield, VA: 41 requests in the PJM queue, 21 active totaling 2,439.7 MW.
A substation with the same name is named in PJM transmission planning materials: Winterpock (DOM, 1 mention).
Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | 360 Solar Center, LLC |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | TC2 |
| Stage | Phase 3 |
| MW energy | 26.0 |
| MW capacity | 15.6 |
| MFO | 26.0 |
| Submitted date | 8/4/2021 |
| Last updated | 8/19/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.