Basin - Chesterfield substation interconnection queue

2 active projects totalling 545 MW in the PJM queue.

2active projects
545active MW
2total filed
Queue IDProjectkVMWResourceStatus
C01-2171 Basin - Chesterfield 230 kV 230 425 Nuclear Active
C01-1543 Basin - Chesterfield 230 kV 230 120 Battery Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.