Chesterfield substation interconnection queue
8 active projects totalling 1,240 MW in the PJM queue, plus 3 with terminal status (shown greyed).
8active projects
1,240active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| X2-082 | Chesterfield 230kV | 230 | 1,420 | Gas | Withdrawn |
| AF1-128 | Chesterfield CT Units 1 and 2 | 230 | 569 | Gas | UC |
| AF1-129 | Chesterfield CT Units 3&4 | 230 | 569 | Gas | Engineering and Procurement |
| AG2-646 | Chesterfield 230 kV | 230 | 200 | Battery | Withdrawn |
| AG2-269 | Chesterfield 230 kV | 230 | 150 | Battery | Withdrawn |
| S79 | Chesterfield Unit #6 | 230 | 27 | Coal | In Service |
| AG2-384 | Chesterfield 230 kV | 230 | 24 | Battery | Active |
| S80 | Chesterfield Unit #5 | 230 | 20 | Coal | In Service |
| R63 | Chesterfield Unit #5 | 230 | 19 | Coal | In Service |
| C01-1087 | Chesterfield 230 kV | 230 | 6 | Gas | Active |
| C01-1088 | Chesterfield 230 kV | 230 | 6 | Gas | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.