Substation Scout

Harrowgate-Locks substation interconnection queue

1 active project totalling 72 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
72active MW
2total filed
Queue IDProjectkVMWResourceStatus
AE1-232 Harrowgate-Locks 115 kV 115 72 Solar Withdrawn
AE2-027 Chester Solar 115 72 Solar Suspended

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.