Stockton substation interconnection queue

2 active projects totaling 75.6 MW in the PJM queue, plus 4 with terminal status (shown grayed).

Target commercial operation dates as filed run from Nov 2017 to Apr 2028 (6 filings). 2 active filings target a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing).

2active projects
75.6active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE2-166 Rocky Ford Solar Energy Center 138 54 Solar Suspended Dec 2026
AI2-137 Stockton 138 kV 138 21.6 Solar Withdrawn Dec 2022
C01-1654 Stockton 138 kV 138 21.6 Solar Active Apr 2028
AC1-117 Leatherwood 34.5 7.6 Solar Withdrawn Dec 2021
AB2-167 Stockton 69kV 69 5.3 Solar Withdrawn Nov 2017
AE2-245 Stockton 34.5 kV 34.5 5.3 Solar Withdrawn Dec 2020

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Henry County, VA

All 19 PJM queue filings in Henry County, VA.

Other PJM queue substations in Worcester County, MD

All 35 PJM queue filings in Worcester County, MD.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first