Substation Scout

Henry, VA interconnection queue

8 active projects totalling 1,573.9 MW in the PJM queue, plus 11 with terminal status (shown greyed).

8active projects
1,573.9active MW
19total filed
Queue IDProjectkVMWResourceStatus
AB2-145 Axton 138kV 138 572 Gas Withdrawn
C01-1714 AXTON 765 kV 765 520 Gas Active
C01-1931 AXTON 765 kV 765 520 Gas Active
AB2-146 Axton 138kV 138 382 Gas Withdrawn
C01-2108 AXTON 765 kV 765 350 Battery Active
AG2-414 Axton 138 kV 138 210 Hybrid Withdrawn
AE2-140 Axton Solar 138 120.7 Solar Pending Termination
AE2-166 Rocky Ford Solar Energy Center 138 54 Solar Suspended
AD2-216 Axton 138 kV 138 43.9 Solar Withdrawn
AE1-100 Caden Energix Axton 138 41.9 Solar In Service
AA2-070 Smith Mountain Hydro 138 34 Hydro In Service
AE2-047 Henry County Solar Facility 69 32.4 Solar Engineering and Procurement
AI2-137 Stockton 138 kV 138 21.6 Solar Withdrawn
C01-1654 Stockton 138 kV 138 21.6 Solar Active
AH1-175 Sheffield 34.5 kV 34.5 12 Solar Withdrawn
AH1-176 Ridgeway 34.5 kV 34.5 11.3 Solar Withdrawn
AG1-468 Martinsville-Figsboro 34.5 kV 34.5 8.4 Solar Withdrawn
AC1-117 Leatherwood 34.5 7.6 Solar Withdrawn
AE2-245 Stockton 34.5 kV 34.5 5.3 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.