Worcester, MD interconnection queue

4 active projects totalling 5.1 MW in the PJM queue, plus 31 with terminal status (shown greyed).

4active projects
5.1active MW
35total filed
Queue IDProjectkVMWResourceStatus
T122 Ocean Bay 138kV 138 120 Offshore Wind Withdrawn
AH2-337 Talbot 69 kV 69 80 Hybrid Withdrawn
AD2-212 Ocean Bay 128 kV 128 70 Offshore Wind Withdrawn
AH2-336 Kenney - Mt Olive 69 kV 69 70 Hybrid Withdrawn
AJ1-018 Bishopville – Worcester 138 kV 138 39 Hybrid Withdrawn
AB2-120 Piney Grove-New Church 138kV 138 38 Solar Withdrawn
Z2-070 Worcester-Ocean Pines 69kV 69 25 Not reported Withdrawn
AH2-354 Bishopville - Worcester 138 kV 138 18.6 Solar Withdrawn
AH2-379 Sign Post - Stockton 69 kV 69 17 Solar Withdrawn
AH1-380 Mt Olive - Kenny 69kV 69 12 Solar Withdrawn
AA1-140 Worcester 25kV 25 7.6 Solar Withdrawn
W2-099 Kenney 69kV 69 7.6 Solar Withdrawn
X2-045 Kenney-Mt. Olive 69kV 69 7.6 Solar Withdrawn
Z1-123 Piney Grove 1 138kV 138 5.9 Solar Withdrawn
Z1-124 Piney Grove 2 138kV 138 5.9 Solar Withdrawn
Z1-125 Piney Grove 3 138kV 138 5.9 Solar Withdrawn
Z1-126 Piney Grove 4 138kV 138 5.9 Solar Withdrawn
AA1-141 Kenney 25kV 25 5.7 Solar Withdrawn
Z1-076 Stockton 1 69kV 69 5.3 Solar Withdrawn
AB2-167 Stockton 69kV 69 5.3 Solar Withdrawn
L14 Berlin 69kV Tap 5 MW 69 5 Other Withdrawn
W3-071 Worcester 25kV 25 4.8 Solar Withdrawn
AA1-094 Worcester 25kV 25 4 Solar Withdrawn
W3-160 Worcester Solar Facility 25 3.8 Solar Withdrawn
Z1-077 Stockton 2 69kV 69 3.8 Solar Withdrawn
Z2-077 Worcester North 25 3.3 Solar In Service
AB2-177 Kenney 25kV 25 2.5 Solar Withdrawn
AC1-041 Mt. Olive 12kV 12 1.9 Solar Withdrawn
W1-131 Kenney n/r 1.9 Solar Withdrawn
Z2-076 Worcester South 25 1.8 Solar In Service
AC1-049 Worcester 25kV 25 1.5 Solar Withdrawn
AG1-318 Ocean City-Battery Storage 12 0.3 Battery Withdrawn
C01-1869 Ocean City 12 kV 12 0 Battery Active
U3-003 Worcester County Renewable Energy 69 0 Gas Deactivated
X1-032 Somerset Solar Project 25 0 Solar In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.