Lackawanna - Hopatcong substation interconnection queue
3 active projects totalling 3,454.2 MW in the PJM queue.
3active projects
3,454.2active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-1193 | Lackawanna - Hopatcong 500 kV | 500 | 1,430 | Gas | Active |
| C01-2229 | Lackawanna - Hopatcong 500 kV | 500 | 1,309.2 | Hybrid | Active |
| C01-1194 | Lackawanna - Hopatcong 500 kV | 500 | 715 | Gas | Active |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.