Substation Scout

Lackawanna - Hopatcong substation interconnection queue

3 active projects totalling 3,454.2 MW in the PJM queue.

3active projects
3,454.2active MW
3total filed
Queue IDProjectkVMWResourceStatus
C01-1193 Lackawanna - Hopatcong 500 kV 500 1,430 Gas Active
C01-2229 Lackawanna - Hopatcong 500 kV 500 1,309.2 Hybrid Active
C01-1194 Lackawanna - Hopatcong 500 kV 500 715 Gas Active

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.