Lackawanna - Hopatcong substation interconnection queue

3 active projects totaling 3,454.2 MW in the PJM queue.

3 PJM queue filings name Lackawanna - Hopatcong as the point of interconnection, all in PA.

Target commercial operation dates as filed run from Jun 2031 to Jan 2034 (3 filings). 3 active filings target a date after November 27, 2026.

Transmission owner as filed: PPL (3 filings).

3active projects
3,454.2active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1193 Lackawanna - Hopatcong 500 kV 500 1,430 Gas Active Jan 2033
C01-2229 Lackawanna - Hopatcong 500 kV 500 1,309.2 Hybrid Active Jun 2031
C01-1194 Lackawanna - Hopatcong 500 kV 500 715 Gas Active Jan 2034

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Lackawanna County, PA

All 25 PJM queue filings in Lackawanna County, PA.

Other PJM queue substations in Wayne County, PA