Substation Scout

Lackawanna - Hopatcong 500 kV

PJM queue ID C01-1193

Lackawanna - Hopatcong 500 kV (C01-1193) is listed in the PJM interconnection queue as a 1,430 MW gas project in Lackawanna County, PA. The filing names Lackawanna - Hopatcong as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of January 1, 2033.

Queue IDC01-1193
Project nameLackawanna - Hopatcong 500 kV
Status (as published)Active
SubstationLackawanna - Hopatcong
Point of interconnectionLackawanna - Hopatcong 500 kV
CountyLackawanna
StatePA
Voltage500 kV
Capacity1,430 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2033-01-01
Source datasetcycle

Same substation and county

Lackawanna - Hopatcong substation: 3 requests in the PJM queue, 3 active totaling 3,454.2 MW.

Queue IDProjectMWResourceStatus
C01-2229Lackawanna - Hopatcong 500 kV1,309.2HybridActive
C01-1194Lackawanna - Hopatcong 500 kV715GasActive

Lackawanna, PA: 25 requests in the PJM queue, 10 active totaling 3,660.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperInvitium Energy, LLC
Transmission ownerPPL
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy1500.0
MW capacity1430.0
MFO1500.0
Submitted date4/25/2026
Last updated6/12/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first