Lakeville substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Lakeville as the point of interconnection, all in Wayne County, PA.
Target commercial operation dates as filed run from Dec 2023 to Jun 2028 (2 filings).
Transmission owner as filed: PPL (1 filing).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| C01-2208 | Lakeville 69 kV | 69 | 150 | Battery | Withdrawn | Jun 2028 |
| AG2-612 | Lakeville 12 kV | 12 | 4.3 | Hybrid | Withdrawn | Dec 2023 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Wayne County, PA
- Lackawanna - Hopatcong: 3 active, 3,454.2 MW of 3 filed
- East Carbondale: 2 active, 83 MW of 2 filed
- Peckville: 1 active, 1 MW of 2 filed
- Thompson: none active of 7 filed
- East Carbondale-Lackawanna: none active of 4 filed
- Peckville-Jackson: none active of 4 filed
- Hamlin: none active of 2 filed