Substation Scout

Lackawanna - Hopatcong 500 kV

PJM queue ID C01-2229

Lackawanna - Hopatcong 500 kV (C01-2229) is listed in the PJM interconnection queue as a 1,309.2 MW hybrid project in Wayne County, PA. The filing names Lackawanna - Hopatcong as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of June 30, 2031.

Queue IDC01-2229
Project nameLackawanna - Hopatcong 500 kV
Status (as published)Active
SubstationLackawanna - Hopatcong
Point of interconnectionLackawanna - Hopatcong 500 kV
CountyWayne
StatePA
Voltage500 kV
Capacity1,309.2 MW
Resource (as published)Natural Gas,Other,Hybrid
Resource categoryHybrid (normalized for filtering)
Target commercial operation2031-06-30
Source datasetcycle

Same substation and county

Lackawanna - Hopatcong substation: 3 requests in the PJM queue, 3 active totaling 3,454.2 MW.

Queue IDProjectMWResourceStatus
C01-1193Lackawanna - Hopatcong 500 kV1,430GasActive
C01-1194Lackawanna - Hopatcong 500 kV715GasActive

Wayne, PA: 30 requests in the PJM queue, 4 active totaling 1,393.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperForest City ProjectCo, LLC
Transmission ownerPPL
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy1364.899
MW capacity1309.172
MFO1364.899
Submitted date4/27/2026
Last updated6/12/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first