Substation Scout

Jarratt Solar

PJM queue ID AF1-292

Jarratt Solar (AF1-292) is listed in the PJM interconnection queue as a 8.9 MW solar project in Greensville County, VA. The filing names Fields as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of August 29, 2027.

Queue IDAF1-292
Project nameJarratt Solar
Status (as published)Under Construction
SubstationFields
Point of interconnectionFields 34.5kV
CountyGreensville
StateVA
Voltage34.5 kV
Capacity8.9 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-08-29
Source datasetserial

Same substation and county

Fields substation: 3 requests in the PJM queue, 2 active totaling 17 MW.

Queue IDProjectMWResourceStatus
AG1-532Fields 28.1SolarUnder Construction
AF2-299Jarratt Energy Facility 210.8SolarWithdrawn

Greensville, VA: 58 requests in the PJM queue, 14 active totaling 1,973.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy14.9
MW capacity8.94
MFO14.9

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.