Elwood substation interconnection queue
3 active projects totalling 1,535.9 MW in the PJM queue, plus 1 with terminal status (shown greyed).
3active projects
1,535.9active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AC1-204 | Jackson Generation | n/r | 1,115.9 | Gas | In Service |
| C01-1311 | Elwood 345 kV | 345 | 300 | Battery | Active |
| AE1-070 | Elwood 345 kV | 345 | 135 | Gas | Withdrawn |
| AD2-194 | Jackson Generation | 345 | 120 | Gas | Partially in Service - Under Construction |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.