Substation Scout

East Towanda substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 5 with terminal status (shown grayed).

Target commercial operation dates as filed run from Jun 2017 to Dec 2026 (4 filings).

Transmission owner as filed: PENELEC (1 filing).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
A48 East Towanda 230kV 230 750 Gas Withdrawn n/r
AH1-720 East Towanda 230 kV 230 60 Gas Withdrawn Dec 2026
AI2-022 East Towanda 230 kV 230 60 Gas Withdrawn May 2025
AF2-197 East Towanda 115 kV 115 40.3 Battery Withdrawn Oct 2022
AA2-135 East Towanda 34.5kV 34.5 19.9 Gas Withdrawn Jun 2017

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Union County, NJ

All 40 PJM queue filings in Union County, NJ.

Other PJM queue substations in Bradford County, PA

All 52 PJM queue filings in Bradford County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first