Towanda substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Towanda as the point of interconnection, all in Bradford County, PA.
Target commercial operation dates as filed run from Oct 2011 to Dec 2012 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| U3-010 | Towanda | n/r | 15.6 | Wind | Withdrawn | Oct 2011 |
| V3-018 | Towanda 115kV | 115 | 9.8 | Wind | Withdrawn | Dec 2012 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Bradford County, PA
- E. Towanda: 2 active, 765 MW of 2 filed
- Mehoopany: 2 active, 64.5 MW of 3 filed
- Ontelaunee: 2 active, 33.6 MW of 5 filed
- Grover: 2 active, 21.4 MW of 2 filed
- Milan: 2 active, 21 MW of 4 filed
- Canton: 2 active, 21 MW of 2 filed
- Mansfield-S. Troy: 2 active, 20 MW of 2 filed
- Bradford: 1 active, 1.5 MW of 2 filed
- East Towanda: none active of 5 filed
- East Towanda-Grover: none active of 3 filed
- East Sayre: none active of 2 filed
- North Orwell: none active of 2 filed
- Tennessee Gas-East Towanda: none active of 2 filed